OEE Calculation

In theory, OEE is the ratio of fully productive time to planned production time. In reality, OEE is calculated in terms of its three contributing factors: availability, performance, and quality. These three factors are multiplied together in the OEE calculation to produce a percentage score. Because of this multiplication, deficiencies in any area are severly multiplied. For example, if all three factors are 90%, your overall OEE would only be 72.9%. Studies indicate that the average OEE rate in manufacturing plants is around 60% and around 85% for "world class" facilities.

OEE Calcuation Factors

As mentioned above, three factors are used in the calculation of OEE - availability, performance & quality.

Availability

Availability is a function of planned production time and actual operating time (i.e. planned minus unanticipated downtime):

Availability = [Operating Time] / [Planned Production Time]

Performance

Performance accounts for speed loss and can be calculated one of two ways - either in terms of ideal cycle time or in terms of the ideal run rate. Either way, the calculation is capped at 100% to minimize the affect of any errors in the ideal cycle time or ideal run rate.

Performance = [Ideal Cycle Time] / ([Operating Time] / [Total Pieces])
- or -
Performance = ([Total Pieces] / [Operating Time]) / [Ideal Run Rate]

Quality

Quality is simply calculated as the percentage of good parts produced:

Quality = [Good Pieces] / [Total Pieces]

OEE

Finally, OEE is calculated as the product of the other three factors:

OEE = [Availability] x [Performance] x [Quality]

Other OEE Considerations

Remember that OEE is not a magic number - just because one facility or shift has a higher OEE than another doesn't necessarily mean it is better. For example, increasing availability by 5% while decreasing quality by 3% would result in an improved OEE - but probably not a more profitable operation. This is why each of the three factors should be considered individually as well as the aggregate OEE figure.

 

Want More Information on OEE CALCULATION?

Contact Us Today!

Feature OEE Article in MiBiz

Manufacturers use OEE to improve performance
Monday, July 24, 2006
Read News Article»

 

 

 

 

CSIA Control System Integrators Association

Material Handling Systems | Process Control | Production Efficiency | Current Projects | OEE | Andon
©2009 Control Dynamics, Inc. All Rights Reserved.
Website D
esigned by
Grand Rapids Website Designer Indezyn, LLC